What's the process of making an asset inventory on a tablet?

The core of asset management is to move the "book" and "physical objects on the same screen. Take the table, and go next to the asset, sweep the bar code or RFID tag, and software immediately tell you which department this device is registered with, what its original value is, whether it's "in use" or "inactivity." The whole process is not handwritten, and no back-entry is required.

Most flat-board asset management software is three steps in the inventory process: first, it is to get an initialization from Excel or ERP; then take the tablet to the field scan; and finally, it is to be sent back to the server to generate a record of the gain and loss report.

What's the difference between a big screen count and a single-person sweep?

One person can scan a few hundred to a few thousand office assets at their own pace. But in a factory with more than 10,000 machines, a campus with dozens of buildings, or a school or hospital with equipment spread across many rooms, a single pass can take several days and data transmission is more prone to interruptions.

The big screen count mode is: put a large screen in the conference room or warehouse entrance, and then take an entire campus's assets, take a count of progress, project out the abnormal items in real time. Multiple boarders are also carrying tablets, scan data back to the server by WiFi, jumps on the big screen -- how many have been cleaned, which area has left a missing spot, which assets are not in the right state. Which sets will be taken on the scene that day.

The advantage of this model is "clan-by-side decision." In a million-scale park project, single-person sweeps are usually only at about 30 percent in the first two days, and on the third day they switch to big screens, two count groups push together, and then we can pull up to 85 percent in the afternoon, with the remaining long end assets located directly on specific floors.

What's the field check? How do we handle "The Books Can But Not"?

On-site verification is not simply "sweeping, if you can't." The standard check depends on four things:

When you encounter an asset that is not right, the tablet supports three types of tag: a gain (actually there is no record), a loss (on the books, not available on site), an abnormal state (such as registration "in use" but actually sealing). Every anomaly is taken live, positioned, notes are written to be used as a basis for subsequent processing. Don't let inventory counting officers in the field judge whether this is lost or transferred, which is an asset management job.

Where the network is bad, will the tablets be stuck?

Yes, this is a relatively large number of pits that have been stepped on in the project. Factory workshops, underground parking areas, remote school areas, WiFi signals are often intermittent. The selection depends on whether the software supports offline mode: downloading the data from the same day's drive to local locations, and then scanned it properly when the net is cut off, taking photographs, marking anomalies; and when you return to the area where there is a signal, the data automatically synchronized back to the server.

Two other details are easy to overlook. A tablet battery must last at least eight hours of continuous scanning; one operator can scan three or four hundred tags in a morning. Ordinary scanners cannot read the tags on metal cabinets, so UHF RFID is needed to read through. Confirm both points before getting to the site.

How do you match the financial records with the data after the count?

This is why many companies have finished their inventory without actually "used it." After the inventory report is produced, at least three things are to be done:

  1. Send the list of surplus and loss to asset managers for confirmation on an item-by-article basis, so that direct eliminations from the transfer order can be found and undiscovered slips are not available
  2. Synchronize depreciation due and change in equipment status to ERP or financial systems to avoid long-term disconnections
  3. A reset of the indicators for the inventory process itself — average number of units per hour per counter, how much is unusual and which type of asset is most easily unattainable, and these data are used to optimize the strategy for the next round of inventory counts

When Shanghai Picker Technologies Ltd. landed on projects like this, the third step of the retrodiscendment was often a more valuable part. For example, when certain types of assets had high quarterly anomalies, they were found to have been caused by the transfer process not going through the system -- which would have helped management better than simply matching the book numbers.

What are the three things to prepare before you do it?

First, the asset desk account is first cleared in a round.The inventory was not available, but it had to be disposed of before the inventory was started, otherwise hundreds of losses would have occurred and the inventory would have been undetected.

Second, the labelling and coding rules are harmonized once.Barcodes, RFID, mixed two-dimensional code can lead to a confusion in the scanning process, and it is best to identify a major option at the initialization stage.

Third, the inventory route is planned in advance.Select one of the three sub-categories by floor, by sector and by asset type, and do not switch from one to another, otherwise data can be very painfully aggregated.