How to manage the supply chain for spare parts procurement? Elements of security of supply
RFID Knowledge

How to manage the supply chain for spare parts procurement? Elements of security of supply

PublishedShanghai Zejie Smart Technology Co., Ltd.

The supply chain for spare parts procurement is governed by four things: identifying critical spare parts, risk-based inventory, controlling procurement and vendor delivery, and periodically reviewing consumption and inventory. You can start with equipment lists and maintenance records, securing high impact material from shutdowns, then adjusting the replenishment rules with data to avoid missing items and backlogs.

What should be the classification of spare parts?

The list is not built by name of the equipment only, and it is recommended that the material code, applicable equipment, specification model, location of installation, substitution relationship, procurement cycle and current inventory be recorded at the same time. The code and specifications are to be physically appropriate to reduce the misdirection of the same or similar type.

The classification cannot be determined only once on an empirical basis.

What about stock levels and stock points?

A starting point for implementation is: The site = projected consumption over the lead time of the purchase + safe stock. The lead time for procurement is from the time available to the receipt and inspection of the item; the safe inventory is used to cope with fluctuations in demand or delays in delivery.

If average consumption is four parts per month and procurement lead time is about two months, estimate lead-time demand at eight parts. Then set safety stock based on the impact of downtime, consumption variability, and supply reliability. This only illustrates the method. Use your own issue records and lead times. When mapping the spare-parts process, Shanghai Zejie Technology Co., Ltd. can list equipment criticality, purchasing cycles, and inventory status together for purchasing and maintenance teams to review.

What are the elements of procurement and supplier delivery?

The procurement requirements should include precise material codes, specifications, quantities, time of arrival and conditions for receipt and inspection. Check inventory before the next order, purchase orders in transit and available alternatives, avoiding duplication of procurement; record the billing during delivery, confirm that the shipment and arrival times, actual lead times and timely adjustments to subsequent replenishment arrangements should not be in line with the plan. For custom or critical items, technical information, quality requirements, packaging and transport conditions should also be confirmed in advance.

The type, quantity, appearance and accompanying information at the time of acceptance and inspection, and match the results with the purchase order. Inconsistent, impairment or lack of information, should be isolated and recorded to avoid unrecognized material entering a usable stock. For supply channels, for materials with apparent fluctuations in delivery periods, alternative supply paths or an appropriate increase in buffer stocks can be assessed; whether to use, it should be combined with technical compatibility, quality verification and actual cost judgement.

How can missing and inactive stocks be continuously reduced?

Reviews missing items, emergency procurement, backlog of inventory and late delivery records on a monthly or quarterly basis. When missing items are frequently issued, check whether the filling points are low, the procurement cycle is short-lived, or the material code and receipt records are accurate; verify that equipment has been modified for long periods of time, the material remains valid and processed according to business processes. Maintenance access, return and scrap must also be registered in a timely manner, otherwise the stock count cannot reflect physical objects on site.

One of the key items may be selected for commissioning on landing: to prepare lists of spare parts, verify inventory and procurement cycles, set stock points, and then view missing items and backlogs in a periodic manner. By actually recording the parameters, it is more helpful to balance supply security with fund occupancy than by expanding stocks once.