How do we control spare parts? Inventory and access to all-process controls.
RFID Knowledge

How do we control spare parts? Inventory and access to all-process controls.

PublishedShanghai Zejie Smart Technology Co., Ltd.

The core of spare parts management is not "the more secure the better the better the better the better the better the better." It is to keep the stock at a reasonable level while ensuring that the equipment is not running. The whole process control answers four questions: what to do, how much to do, who to take and how to back. The answer lies in three layers of the principles of the parts classification, inventory algorithms and access closed loops.

The most common area of error in spare parts management: "Be prepared" is everything.

Many factories have spare parts that look full, but when equipment fails, key items are often not found; unconventional pieces pile up a warehouse. This "unusual and undesirable mountain-stacking" is common.

What's the problem? Most managers equate spare parts control with "purchase in" to "buy in," so that we can build a warehouse, fill out a desk. But spare parts go from stock to consumption, and there are classifications, inventory strategies, access approval, write-off of a vault, and each one loses its way ahead.

For example, a food-packing plant with spare parts stores that consume thousands of materials per year, but the failure rate is not dropping. In in-depth checkup, it turns out that most of the stop time is concentrated on a few critical spare parts shortages, which are either not ready or were not returned in time.

First tier: the principle of identifying which spare parts are worth preparing and which need not be stockpiled

The first step in the control of spare parts is not to count stocks, but rather to classify them. The degree of importance, difficulty of procurement and consumption patterns vary widely among different spare parts, and problems arise from the same standard management.

More mature in the field of exercise is the ABC classification, which is divided by the amount and the proportion of the variety:

The photos are not enough, but they have to be superimposed on a dimension: critical levels. They're also the bearings, which are installed on the main line and on the back-up pump, and they're completely different. The former is ready to wait for days. The key high parts, even if small, are managed separately.

Second level of the theory -- not a headshot, basic algorithm.

The next question, after the classification has been completed, is: how much each spare part is available? Here are two basic parameters that can be consulted.

Reordered Points (ROPs) = Average daily consumption x Purchase advance + Safe stock. This means that when inventory is down to this number, a new bill will be drawn up or the equivalent period may be broken.

Secure inventory (SS) = Average daily consumption x advance procurement x service level coefficient. The higher the level of services required, the greater the coefficient. The 95% supply security rate is requested, the factor is taken 1.65; 99% is required, the coefficient is 2.33. These figures are from the standard normal distribution table, which is common to industry.

For example, a spare part is used at an average rate of two units per day, takes seven days to procure, and requires a 95% service level. Safety stock = 2 × 7 × 1.65 ≈ 23 units, and the reorder point = 2 × 7 + 23 = 37 units. Place an order when stock drops to 37 units. When it arrives, stock will rise to around 60 units, enough to cover consumption in the next cycle and the safety reserve.

Of course, the formula is only the starting point. It takes into account the supplier's stability of delivery (some suppliers write contracts for 7 days, which are actually often delayed to 14 days), seasonal consumption fluctuations, and equipment life-cycles. When Shanghai-based Sieggers optimized their spare parts inventory, they usually cross-check these data and adjust their parameters, avoiding a formula that looks pretty but does not work.

The third level of the principle -- the access chain is the black hole where spare parts are lost.

The first two steps are ready, and if the access chain is not in place, the effect will be zero. The core of the access control is three things: who's going to do it, how to do it, how to do it.

Level of approvalThe application of category A spare parts requires approval by the equipment manager or above, approval by the head of the B workshop and direct delivery by the C-collars. This avoids the immediate removal of tens of thousands of spare parts from front-line staff and allows for retroactive liability for use.

First in advance (FIFO)Spare parts are "preserve" (for example, rubber seals, lubricant, electrical components will not be ageing or even failing for long). The access is to be issued in the order of time in which they are stored, and the old ones are used first, so that they do not run out. In reality, many factories have tens of thousands of dollars worth of sealed spare parts, but a large quantity of them has passed the warranty period, and then only a whole lot of them can be scrapped, with considerable losses.

Refund write-offs: Check unused spares back into stock. If you take 10 bolts and use six, scan and return the remaining four instead of letting them become off-book stock in a personal toolbox. Many plants skip this step, and records drift away from actual stock until a count reveals a large gap.

Three-layered principles: data flow and regular rediscretion

The three layers of classification, inventory strategy, access control are not isolated, and data flow is required to create a closed loop. Specifically: purchasing the inventory data from the repository automatically updates the inventory, taking out the library in real time deductions, re-entry and scrapping adjustments, each change being checked on a single account.

On this basis, a regular re-entry is also required.

If an indicator is permanently off target, then the back check is not a good sort of thing, the parameters are not reasonable or there is a loophole in the access. Putting diagnostics and improvements into a fixed rhythm, the spare parts management is going to be better, not a temporary fire-fighting time for each lack of supplies. It's no longer difficult to take all three layers of this into account.