How is the project spare parts management programme prepared? Project delivery packages
The project spare parts management programme is not "over-purchased" simple, with the core being to set the list by type of equipment, frequency of failure, supply cycle and hand over simultaneously at delivery.
I. Scope determination: Are all projects to be part of the spare parts programme?
This is the first question to be answered before the preparation of a full programme or only a simplified list. The following categories of situations suggest that they be done by normative programme:
- (a) High non-standardization of equipment: the original plant ' s spare parts supply cycle may last for 8-12 weeks if there is a problem with custom equipment;
- (a) Remote location of the project: North-West, North-East and Overseas projects, long logistics cycles, high emergency supplement costs;
- For a piece of equipment costing over CNY 500,000, 1–3% of total equipment value is a reasonable spare parts budget;
- After delivery, there are 12-24-month protection requirements: spare parts must be in place with the project.
The test is simple: the more sensitive the project is to "cut-off," the more detailed the spare parts programme. The more standardized the vendor is locally, the less than 100,000 small items, and it's enough to make an Excel list of all the shipments.
II. List of spare parts: full or fine?
Many of the lists either omit key items or have a list of unserviceable ones. The standard way to classify spare parts is to divide them into three categories, by "frequency of use x degree of importance", and to apply different spare parts strategies for each category:
| Category | Characteristics | Typical | Spare parts ratio reference |
|---|---|---|---|
| Vulnerable items | Periodically replaced, with short life expectancy | Seal, filtration, belts, bearings. | Based on 2-3 replacement cycles |
| Consumable | Gradual consumption with use | Lubricating oil, welding, knife utensils | Based on 1 year of availability |
| Critical spare parts | The failure has a high impact, long supply cycles | Frequency changers, PLC modules, sensors | 1-2 items, depending on the supply cycle |
The list must contain 9 items of information: name of equipment, installation number, name of spare parts, specification type, plant, quantity, unit, unit price, storage requirements, and trouble without a subsequent handover.
Quantitative estimates: more or less?
This is the most difficult step – wasteful and insufficient. The three common approaches have a different set of scenarios:
Experience Law: refer directly to the replacement records of the same type of project over 2-3 years. The simplest, but only for companies with historical data accumulation, not for new types of projects.
Life expectancy method: Responds according to the lifetime of spare parts and the annual running time of equipment. For example, a filter core has a 2000-hour life, 16 hours per day for equipment, 300 days per year, which consumes about 2.4 in that year and is provided by 3. Logically clear but requires accurate performance data.
Vendor recommendation method• Send the proposed list to the plant or spare parts supplier. The most economical, but often overstated by the vendor, especially non-teams, so that the final amount is reviewed at a 7-8 discount.
The actual items are usually used in combination: the useful lifetime calculation of vulnerable items, a further discount on key items recommended by the supplier, and a one-year amount for consumption items directly based on experience. In delivering the automated production line project, Shanghai has generally provided 80% of spare parts for critical electrical components, combined with 12 months' protection period - 1-2 months' coverage, 24 months' supply of 2-3.
IV. Quality of delivery: delivery on delivery or late delivery?
Many projects are delayed until they are accepted and received. Temporary purchases often fail to meet the schedule.
- Packing Method(a) A stand-alone box for spare parts, marked with the words "reserve spare parts", numbered separately from the main equipment to avoid confusion with the mainframe;
- Attached documents(a) A list of each box of spare parts and a general list of the spare parts set, to be archived as an annex to the delivery information;
- Storage requirements(i) Lists of temperature and humidity, dust-proofing, tidal-resistant conditions, and inappropriate storage of electronic components and precision sensors is equivalent to direct end-of-life;
- Handover of signatures(b) Hand over of separate receipt and receipt, signed by the user ' s warehouse or owner of the equipment, and separated from host acceptance and inspection.
The advantage of this is that the late-maintenance security can be reconciled quickly – which spare parts are used, which ones are not used, and which need to be replenished, all are documented.
V. Common pits: mined areas easily trampled upon in preparation and delivery
- The inventory and the actual equipment are not up to date.: The list was not updated after an equipment change, so the wrong spare model arrived. Review the final list again seven days before shipment;
- No trace of spare parts from the original plant(a) Spare parts not included in the "compatible XX" type, which must be a substitute for the original plant or written authorization of the manufacturer;
- Ignore small pieces(a) Low unit price of bolts, gaskets and seals but not fit in if one is missing, and the whole equipment may be lying down;
- No contact with the security team.: The list was prepared without the advice of the user protection team, who is most aware of the historical failures and often can fill in the critical ones;
- Lack of annexes for delivery of informationThe spare parts list, the packing list, the certificate of eligibility were not included in the delivery package and the receipt and inspection were completed by A-Perceived to slow the completion of the entire project.
VI. Proposals for action
If you are preparing a spare parts programme, it is almost without major error to move in this order:
- (a) Clarify the duration of the project and the supply cycle pressure, and determine whether formal programmes are required;
- (a) Spare parts by three categories against the BOM (material inventory) table;
- The combination uses three quantitative estimation methods, with key items being identified in writing by the supplier;
- Spare parts are included in delivery kits, packed and signed with the host.
The whole process can be completed in 2-3 weeks, not the workload but the level of familiarity with the equipment and understanding of the use. If the project is full of equipment, a variety of types, and delivery cycles are tight, it is recommended that the equipment be evaluated together at the programming stage, and then finalized by three parties, saves 80% of the late-stage treachery.