The common misconception is that the more spare parts are safe, or all materials are covered by the same set of standards. It is more prudent to classify them by value and importance, then to set a threshold on inventory in relation to demand, procurement cycle and impact of missing goods; ABC classification determines the precision of management, with quotas being assigned to downloading the replenishment rules.

First, the value of spare parts and the impact of the shutdowns are distinguished.

ABC classifications are usually ranked according to the amount of the benefit received over a given period: Annual consumption amounts can be calculated as “annually accepted quantities x unit prices”. Cumulative amounts are included in category A, the amount affects intermediate items in category B, and the value effect is lower in category C. The common practice is to treat approximately 70-80 per cent of aggregate amounts as category A, about 15-20 per cent as category B and the rest as category C; these proportions are only initial references, based on the restructuring of the enterprise's material and recording the calibre used.

The amount cannot substitute for a risk assessment of the equipment. The unit price is low, and the amount of specialized parts is small, and if the lack of supplies leads to the shutdown of critical equipment, it also requires an increased management level. The actual classification can be accompanied by a "key" mark that classes the amount with the impact of the stoppage, alternative, purchase cycle, and avoids the simple subprimeization of low-value material.

ABC Decision Inventory and Approval Strength

The classification should be recalculated on a regular basis, rather than being fixed for long periods after a time. When designing inventory management rules, Shanghai-based Tech Ltd. will classify the amount and equipment as critical, and will consider the procurement in advance, so that the count frequency and approval requirements correspond to actual risk, not just to the cost of the material unit.

Converting the quantity of the replenishment to enforceable rules with a quota

The stock quota is not a uniform number for each spare part, but sets the trigger point and target amount based on the need and replenishment time.Reordering point = projected requirements in the lead-up to procurement + secure inventory. The procurement lead time is from the time of the order to material availability; a secure inventory is used to address uncertainties such as fluctuations in demand, delays in delivery, etc.

For example, a part issued at an average rate of four per month with a two-month procurement lead time has lead-time demand of about eight units, before accounting for fluctuations. If the review sets safety stock at three units, the reorder point is 11. Start replenishment when the inventory position drops to 11 units. These figures are only an example. Calibrate actual levels using issue history, maintenance plans, supply lead times, and the consequences of a stockout. Account for pack sizes, order minimums, and quantities already on order when setting the target stock level so you do not order twice.

Let the quota be revised with actual consumption

The process of review focuses on the number of missing items, emergency procurement, stock accuracy, inactive amounts and quota deviations. If a spare part is not used for a long time, confirm whether it still applies to equipment in use, then decide whether to adjust or dispose of it; if there are frequent shortages, examine the estimated needs, deliver and set security inventory.

The core of management is not to press inventory to a fixed percentage, but to find an explanationable and adjustable balance between the use of funds and security of equipment. First, by using ABC classification, then by specifying when, how much, and by regularly amending the rules on inventory, depending on actual access and procurement performance.